NTU kicked off project "Technical Assistance to the Pakhtunkwa Energy Development Organisation" in Pakistan
𝗡𝗧𝗨 𝗸𝗶𝗰𝗸𝗲𝗱 𝗼𝗳𝗳 𝘁𝗵𝗲 𝗽𝗿𝗼𝗷𝗲𝗰𝘁 “𝗧𝗲𝗰𝗵𝗻𝗶𝗰𝗮𝗹 𝗔𝘀𝘀𝗶𝘀𝘁𝗮𝗻𝗰𝗲 𝘁𝗼 𝘁𝗵𝗲 𝗣𝗮𝗸𝗵𝘁𝘂𝗻𝗸𝗵𝘄𝗮 𝗘𝗻𝗲𝗿𝗴𝘆 𝗗𝗲𝘃𝗲𝗹𝗼𝗽𝗺𝗲𝗻𝘁 𝗢𝗿𝗴𝗮𝗻𝗶𝘀𝗮𝘁𝗶𝗼𝗻” 𝗶𝗻 𝗣𝗮𝗸𝗶𝘀𝘁𝗮𝗻
The project will strengthen the capacities of Khyber Pakhtunkhwa Government institutions, principally the Pakhtunkhwa Energy Development Organisation, to integrate long-term climate change adaptation and resilience, as well as environmental protection, into the construction and management of 𝗵𝘆𝗱𝗿𝗼𝗽𝗼𝘄𝗲𝗿 𝗽𝘂𝗯𝗹𝗶𝗰 𝗶𝗻𝗳𝗿𝗮𝘀𝘁𝗿𝘂𝗰𝘁𝘂𝗿𝗲. It contributes to climate-resilient socioeconomic recovery in the districts of Khyber Pakhtunkhwa most affected by the 2022 floods.
The NTU team took part in kick-off meetings at the European Union in Pakistan, in Islamabad, and at the premises of the 𝗣𝗮𝗸𝗵𝘁𝘂𝗻𝗸𝗵𝘄𝗮 𝗘𝗻𝗲𝗿𝗴𝘆 𝗗𝗲𝘃𝗲𝗹𝗼𝗽𝗺𝗲𝗻𝘁 𝗢𝗿𝗴𝗮𝗻𝗶𝘀𝗮𝘁𝗶𝗼𝗻 in Peshawar.
The Project at a glance:
➜ Budget of EUR 3 million and 30 months of implementation
➜ 2 full-time Key Experts and a team of Non-Key Experts, with a total input of 990 days
➜ 8 outputs grouped in 3 pillars: Institutional Strengthening and Governance Systems, Operational Performance and System-Level Service Delivery, and Investment Readiness and Project Preparation
One of the most notable outputs is a minimum of two feasibility studies for small to medium-scale hydropower plants, with a total generation capacity of 50 MW. Study sites will be selected in coordination and agreement with the organisation and the EU.
At NTU, we look forward to delivering this project successfully, building on our experience in Technical Assistance projects in the energy sector.